Status – At a Glance
- 11248: Units rewired: 14/14 | Units closed: 12/14 | Days passed: 17
- 11216: Projected to begin on November 30
- 11220: Waiting for first notice.
Trajectory
Work in 11216 adjusted to November 30. First notice for 11220 planned for Mid-December
Miscellaneous
- Schedule, roadmap, and website updated as of 11/05/2026
Status – At a Glance
- 11248: Units rewired: 8/14 | Units closed: 7/14 | Permits closed: 4/14 |Days passed: 17
- 11216: First notice posted. Walkthroughs are open for scheduling on website.
- 11220: Waiting for first notice.
Trajectory
Project on track to begin in 11216 on November 1st. First notice for 11220 planned for late November/early December
Miscellaneous
- Schedule, roadmap, and website updated as of 10/1/2026
- Photo gallery updated
- Building timelines added to spreadsheet
6mm plastic covers
Expanded dust-proofing