HOW DO I PREPARE?
1. Items you value must be packed. They will not be replaced if damaged.
-Decorations, memorabilia, wall adornments, etc. outside of a box or container.
2. You cannot be in your unit until the end of the first day of work (approx. 5:30PM)
3. Be ready to leave your unit no later than 8am.
-The contractors must enter at 8am. Delays are charged to the unit owner’s account.
4. Have a power bank ready for power shutoffs.
-Power shutoffs typically begin between 11am-1:30pm and last at least 2 hours.
5. All questions must go to Alfonso and/or Mario (Prime Contractor). Do not ask anyone else about the schedule.
6. A full unit repaint is not in the contract, but repaired drywall will be left with 2 coats of white primer.
WHAT YOU WILL NOT LIKE
1. Washer/Dryers that are not connected to the gas line or that push more than 120V will be disconnected.
2. Refrigerators connected to an external water source will be reported to the office.
-If there is a tube running from the fridge to the inside of your wall, that has to be reported to the office
3. The contractors must remove your ceiling fan if it is improperly installed.
-If your fan wobbles and/or lacks a fan box, the county will fail your unit.
HOW LONG WILL IT TAKE?
1. Per-unit project cycle is at least 3 weeks.
-Defined as the time between Rewiring Day and Finishing Day(sanding/priming).
2. Each unit will be closed in the order they were opened.
-Its reasonable to want this project completed ASAP, but finishing your unit faster means someone else stays out of theirs longer.